300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Work is back on after the Australia Day long weekend

I've got this update from Bernard, looks like the progress is nice and steady at the site. Good to see workers back in action after a 4 day long weekend!
- red crane tower section has been positioned on the footing that's being prepared for pouring behind the loading platform on the south side (this happened today, I took a photo this morning with it lying on its side against the west wall)
- more formwork has been built over the last few days in the NW corner. You can see some slab edge forms, and a few set downs where the slab is thicker around support columns.
- more column foundation pits have been dug in a line running across the centre of the site to the South wall near the new crane base
- excavation for the foundation of the large circular column at the SE end of the res tower has begun, but it looks like they've decided to drill around that to reduce vibration affecting nearby works/structures
- the formwork for last week's concrete pour in the res tower lift pit has been removed, with new formwork going up for the next part of the walls for that. Looks like they're going to either leave a void or backfill with dirt/rock, now that they've got a solid foundation in place.

IMG_20160127_173530.jpg