This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you want to get in touch, please email me on
.


Recent Posts

Final update for 300 George Street

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Peek inside the site and more concrete is pumping

Here are a couple of updates from Geoff and Bernard and myself. First Geoff was kind enough to send in some photos from inside the site, have a look it's good to get a perspective from the inside.

12650280_10153920264092498_784794733_n.jpg 12660463_10153920264047498_1750380118_n.jpg


12674604_10153920264017498_1149102305_n.jpg



Here's an update from Bernard on last Friday's progress…
- pumping concrete into the res tower foundation
- reo cages laid out on the new Basement 6 slab to extend columns upward
- more progress on formwork for commercial tower core & Basement 7 slab


IMG_20160205_095659.jpg

…and finally from me - I noticed that concrete is being pumped on the weekend too. There are cement trucks lined up on the North Quay side waiting to unload.

IMG_0484.jpg

IMG_0485.jpg

-i

Sun Feb 7 01:51:07 2016
Photos, Construction, Day, GuestContribution, Concrete