300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 11th April and 15th of April

The commercial tower lift core is well under way now and the hotel tower underground sections are almost complete with it nearly reaching street level this week. Below are more detailed updates sent in by Bernard.
Since Friday:
- the concrete pumping boom has been mounted on top of the commercial tower formwork
- Basement 6 formwork continuing to go up around the commercial core
- advertising added to the hotel core formwork
- part of the Basement 2 slab poured around the hotel core
- pumping concrete for another level of the residential core
- pouring a bit more Basement 7 slab near the commercial core (infill on the south side)

IMG_20160412_091356.jpg

- lifting out dirt with the long arm excavator again
- prep for pouring Basement 2 on the eastern side of the hotel core (this area will be a loading dock, according to the plans released with the DA, which probably has something to do with the silver ducting (?) being laid
- lots of Basement 6 formwork in place around the commercial core now
- prep work for pouring the rest of the Basement 7 slab around the commercial core

IMG_20160413_120005.jpg



- pouring Basement 2 slab (loading dock area)
- formwork going up for rainwater detention tank on far side of hotel core
- still digging dirt out
- still building Basement 6 formwork around commercial core
- it looks like some jacking supports may be in the res core, perhaps they'll be assembling the jacking form there next week

IMG_20160415_115742.jpg


-i

Sat Apr 16 00:14:31 2016
Photos, Construction, Day, GuestContribution