300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 18th April and 22th of April

All three building lift cores are coming up quite quickly now and it looks like the hotel underground floors have finally reached up to the ground level. Below are more detailed updates from Bernard throughout the week…
- It looks like the jacking formwork is being assembled on the residential core this week!
- formwork going up for the loading dock ramp on the far side of the hotel core
- reinforcing being laid for the Basement 6 slab around the commercial core
- prep work for more Basement 7 slabs just south of the commercial core. There's a height difference of 1.4m between parts of Basement 7 midway along the south wall of the commercial core, according to the plans, and you can see reinforcing poking up at the location of the wall
- dirt still being dug out by the long arm excavator in the SE corner

IMG_20160418_101525.jpg

- pouring Basement 7 concrete around the SE corner of the commercial tower
- jacking formwork for res tower core progressing rapidly
- rainwater detention tank walls in NW corner (behind hotel core at top right) were poured yesterday
- formwork going up for loading dock ramp on N side of hotel core
- Basement 6 reinforcing being laid N & W of comm core

IMG_20160419_122036.jpg



- pouring Basement 6 slab around N & W sides of commercial core
- building jacking formwork structure on res core
- digging column foundation holes in SE corner of site, still a lot of dirt & rock piled up there. Perhaps some will be used as backfill around res core lift pit

IMG_20160421_104040.jpg


-i

Sun Apr 24 20:20:38 2016