300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 25th April and 29th of April

Here are some updates from last week from Bernard. Lots of work at the site! I am still amazed how quickly the lift cores are going up!

27th April -
- pouring another level of the hotel core
- formwork going up for Basement 1 slab in NW corner (some of which is very close to the North Quay Street level)
- post-tensioning appears to have been carried out on the Basement 2 loading dock slab, as there appear to be a lot of trimmed off ends of the tensioning bars lying on the slab near the N site boundary
- prep work for pouring the rest of the Basement 6 slab around the commercial core
- jacking formwork for the res tower core progressing well
- two small excavators hammering out rock in the SE corner, with some column foundation holes dug. Not sure how they're going to lift out the rest of the spoil from there, it would make sense to use a lot of it as fill around the res tower lift pit - that's a big hole to fill to get up to Basement 7 level.

IMG_20160427_132104.jpg


29th April -
- formwork for Basement 1 slab going up in the NW corner near North Quay
- formwork supports for Basement 5 slab starting to go up between hotel area and commercial core
- still digging dirt in the SE corner
- formwork shutters being craned into position for the res core jacking formwork