300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 6th June and 10th of June

Not as much progress this week probably due to the break in over the last weekend, however the broken equipment seems to have been replaced now. See more detailed updates from Bernard below.

7 June -
- part of the slab over the loading dock was poured, along with a large amount of very thick heavily reinforced concrete along the Ann St edge of the site
- gravel spread over part of the podium area, suggesting the Basement 7 slab will be poured there soon

IMG_20160607_165909.jpg


10 June -
- a new dump truck & third excavator are on-site, replacing the ones damaged during the break in last weekend
- the Res core has climbed a level for the first time (somewhere about 90 to go, I think)
- the column foundation where the truck fell in has been poured, and the formwork is in place ready to pour the first level of the column
- plastic membrane and reinforcing in place to pour the first bit of Basement 7 in the podium area
- pouring of Basement 3 slab underway north of the commercial core
- Basement 3 formwork complete around commercial core, reo being laid for the second portion
- formwork shutters in place for a large box to the north of the hotel core. I think this is where the grease traps are marked on the plans
- lots of scaffolding in the porte cochere area SW of the hotel core, getting ready to set up formwork for the slab above

IMG_20160610_090906.jpg




-i

Mon Jun 13 16:02:39 2016
Photos, Construction, Day, GuestContribution