300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 20th June and 24th of June

Here are some updates from Bernard for the past week.

21 June -
- safety cages all gone between the hotel & commercial areas
- lots of Basement 2 formwork up in commercial area
- the last bit of Basement 3 has been completed near the commercial core
- lots of formwork going up over the porte cochere area. Not sure what level this is, will have to check the plans
- lots of spoil has been dug out from beneath the loading platform on the south side
- it looks like there's going to be a strip of concrete poured around the site perimeter near the res core before the rest of the basement 7 slab gets poured there

IMG_20160621_095310.jpg


23 June -
- looks like no work today
- formwork going down for slab above porte cochere
- a level of the hotel core was poured yesterday, as well as the commercial core. Pretty sure there was a pour of the res core on Tuesday afternoon
- Basement 2 formwork 2/3rds done around commercial core
- waterproofing and reo laid around SW edges of site near res core, looks ready to pour Basement 7 slab for that strip
- more column foundations have been dug in podium area
- not much dirt left to dig out from under the southern loading platform

IMG_20160623_115930.jpg




24 June -
- formwork is getting up well above ground level on the Ann St side (I think the big box is for the carpark exhaust risers)
- the res core has climbed another level since yesterday
- pouring concrete around the fire stair and a retaining wall along the height change in the basement 7 level in the podium area. I suspect this will allow them to pour the rest of the basement 7 slab East of that height change someone next week
- still no pour of the basement 7 slab around the SE corner