This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 27th June and 1st of July

Lots of updates this week, probably the largest weekly update so far. Check out the details from Bernard below.
Don't forget to vote today too - and make your vote count!

27 June -
- looks like no work today
- the basement 7 slab around the SE corner (near the res tower) has been poured over the weekend
- gravel being spread in the eastern half of the podium area, the next step will be waterproofing and reo before the slab is poured
- reinforcing being laid for the Western part of the basement 2 slab near the commercial core
- there's some scaffolding standing on top of the basement 2 formwork at the NE corner of the commercial tower. The slab levels get a bit complicated for Basement 2, and the carpark ramp that's at this location on lower floors isn't present, so I think that scaffolding will support part of Basement 2. Not sure where the slab level will be to the north of it, the formwork level doesn't seem to match the drawings I have.

IMG_20160627_114018.jpg


28 June -
- you can see a vertical bit of formwork being erected just NE of the commercial core - this is where there's a difference in the slab height
- reinforcing and post-tensioning cable ducts being placed for the rest of the loading bay on Basement 2, just west of the commercial core
- waterproofing being laid for the Basement 7 slab on the E side of the podium area, and gravel being spread further west
- in the far NW corner behind the hotel core, you can see a curved line in the formwork. This is the base of the above-ground facade for the hotel

IMG_20160628_143154.jpg




30 June -
- formwork build continuing around hotel. The scaffolding & some formwork is now visible above ground when viewed from street level at the corner of George & Ann Streets (see attached pic)
- loading bay reinforcing well underway between hotel & commercial core
- a strip of concrete has been poured just inside the slab around the SE corner of the site. There was an excavator digging a trench around here a day or two back, no idea what this is for
- Basement 7 has been poured on the eastern side of the podium area (the 'upper level' of the basement floors). There's a bit that looks slightly unfinished at the northern end, this is where the ramp will be to Basement 6
- excavator hammering out drainage trenches between podium area and res core
- a walkway has been attached at the top of the pit wall along the southern side, between the site building along George St and the loading platform
- plastic waterproofing is being laid down around the res core, getting ready for Basement 7 slab
- gravel is being spread in the podium area between the nearest tower crane and the southern loading dock, will probably be a slab poured here soon too
- formwork supports for Basement 2 carpark slab East of the commercial core are going up quickly
- reinforcing / post-tensioning ducts being placed for the remainder of the basement 1 slab north of the hotel
- the large black box near Ann St is the formwork shutters for the inside of the car park exhaust riser. I think this vents out a few floors above Ann St, but I haven't checked the drawings


IMG_20160630_091716.jpg IMG_20160630_133332.jpg


1 July -
- plenty of formwork activity around the hotel & commercial cores
- basement 2 formwork nearly done around commercial core
- gravel and waterproofing going down for the Western half of Basement 7 in the podium area
- lifting out rubble from the northern side of the res core - probably not much left to come out
- gravel & waterproofing ready around the southern & western sides of the res core

IMG_20160701_135353.jpg


-i

Sat Jul 2 14:53:10 2016
Photos, Construction, Day, GuestContribution