300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you want to get in touch, please email me on
.


Recent Posts

Final update for 300 George Street

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 18th July and 22nd of July

Here are some of the updated from Bernard for the past week. It was quite foggy in Brisbane during the week with two days having very heavy fog, one of the photos shows this. Check out my previous post earlier on the week that shows how heavy the fog was.

18 July -
Looks like no construction going on today, just a crew putting signage banners on the commercial core formwork

- the podium level slab on the west side of the hotel core has been poured
- looks like reinforcing is ready for the last Basement 7 pour near the res core, and the first Basement 6 pour in the podium area

IMG_20160718_101828.jpg


20 July -
- more reinforcing going in for the next part of the podium level slab around the hotel core
- columns being poured and walls being built in the northern part of the basement 2 slab near the commercial core (I think this is the substation area)
- the last bit of Basement 7 has been poured near the res tower, so the 'floor' of the site is now complete, apart from a small area around each crane tower
- the first part of Basement 6 was poured in the podium area yesterday, lots more formwork in place for the rest of it there and on the western side of the res core


IMG_20160719_092127.jpg IMG_20160720_165221.jpg




21 July -
- more formwork everywhere
- basement 6 formwork is rapidly surrounding the res core
- a mobile concrete pump is setting up on the southern loading platform
- assorted concrete block walls being built just north of the commercial core, to form various rooms and corridors (I think these will be core filled when the slab above is poured)

IMG_20160721_110744.jpg


-i