This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 25th of July and 29th of July

Quite a big update for the past week from Bernard. Check out how high the NW crane reaches now in the pictures for the 28th of July. It's still not over the height of the 'Quay Central' building but is not far off!

25 July -
- new slab poured on north side of hotel core (I think this is podium 2 level)
- more low walls built to north of commercial core (under substation?)
- two crane tower sections stacked near base of large crane, in prep for raising it
- a third crane segment is on the western loading platform
- comparing photos, it looks like the crane in the north-west corner was raised over the weekend

IMG_20160725_095354.jpg


26 July -
- podium 3 formwork going up West of hotel core
- more block walls going up in substation area north of commercial core. I think they must be planning to build a suspended floor slab here, as the walls are fully enclosing large areas with no openings
- reinforcing being placed for last bit of Basement 2 on East side of commercial core
- pouring basement 6 on the east side of the podium area
- reinforcing is ready for the rest of Basement 6 in the podium area, and is being placed south and west of the res core
- the res core has jacked up a level since yesterday
- the crane tower segment that was on the west loading platform yesterday is gone. None of the cranes appear to have been raised since yesterday, though.

IMG_20160726_112829.jpg


27 July -
- block walls in substation area almost complete (core filling them this afternoon)
- pouring last part of basement 6 slab in podium area
- formwork going up for Basement 1 west of commercial core
- crane in NW corner has been raised quite a long way since yesterday! So far it's out of the shot of the rest of the site.

IMG_20160727_103927.jpg




28 July -
- pouring basement 2 slab East of commercial core
- block walls under substation were core filled yesterday afternoon
- formwork, formwork, everywhere… :-)


IMG_20160728_095626.jpg IMG_20160728_100012.jpg


29 July -
- formwork in the NW corner is getting pretty high above North Quay now
- steel sheet formwork being placed in substation area north of commercial core (this is 'sacrificial' formwork that stays in place as part of the slab that's poured on top of it, and acts as reinforcing to a certain extent, I think)
- pouring basement 6 slab on the west side of the res core
- building formwork for the fire stair and carpark ramp in the podium area

IMG_20160729_091221.jpg


-i

Mon Aug 1 17:27:57 2016
Photos, Construction, Day, GuestContribution, Crane