300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
I'm looking for someone to acquire and take over 300george.com. This has been an amazing blogumentary project but I simply do not have the time to keep it going. If you're interested, please email me offers at .
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 15th of August and 19th of August

Here's an update from last week, quite a bit of work done. The commercial tower is almost at the street level now. The hotel tower is well above street level at this point and the residential tower is still quite deep in the pit.

16 August -
- slab poured on the west side of the hotel core
- slab poured on the west & south sides of the commercial core
- first part of basement 5 slab poured in the podium area
- basement 5 formwork has nearly covered basement 6 around the res core

IMG_20160816_090516.jpg


17 August -
- reinforcing being placed on the rest of the formwork around the hotel core
- looks like they've been pumping concrete into columns
- currently pouring the smaller lift core / columns north of the commercial core
- formwork still going up around the res core
- reinforcing being placed for remaining sections of Basement 5 in the podium area, with some Basement 4 formwork supports going up
- fire stair formwork is assembled ready to be poured

IMG_20160817_132647.jpg


19 August -
- reinforcing / post-tensioning ducts going in North/south of hotel core
- blockwork wall going up on South side of substation area
- some Basement 1 formwork supports visible north of commercial core
- Basement 5 formwork largely complete around res core
- pouring last bit of Basement 5 slab in podium area, basement 4 formwork expanding

IMG_20160819_103022.jpg


-i

Sun Aug 21 20:02:56 2016
Photos, Construction, Day, GuestContribution