300 George Street Blogumentary
300 George Street
Brisbane, Australia
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to

You can also contact me via the FaceBook page:
300 George Street Brisbane

Recent Posts

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development

Updates between 29th of August and 2nd of September

Here's the update for the past week. It comes to you from a higher elevation than the previous updates. Enjoy!

29 August -
- slab poured on East side of the res tower core


30 August -
- pouring both commercial and residential cores
- it looks like the res core is connected to a mobile concrete pump parked in the loading zone along North Quay
- more steel formwork going in on the northern edge of the substation


31 August -
- post-tensioning ducts being laid on north side of hotel core
- building formwork around commercial core
- pouring columns around res core
- building formwork in West side of podium area
- laying reinforcing for Basement 4 on East side of podium area
- assembling formwork for fire stair in podium area


1 September -
- Pouring concrete on the hotel core
- the bit of the substation floor against Ann St, north of the commercial core, has been poured
- formwork going up north of the res core for Basement 4
- pouring the next level of the fire stair in the podium area



Sun Sep 4 01:24:04 2016
Photos, Construction, Day, GuestContribution