300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
I'm looking for someone to acquire and take over 300george.com. This has been an amazing blogumentary project but I simply do not have the time to keep it going. If you're interested, please email me offers at .
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 5th of September and 9th of September

Here's an update for the past week. There was a little mix up with some of the photos so not all of them are shown for each of the days, but the general progress is there. The 'no work' day photo looks really cool with all the cranes pointing straight up!

5 September -
- hotel core has jacked up since last Thursday
- slab poured on north side of hotel core today
- reinforcing & post-tensioning ducts going in around commercial core for Basement 1
- res core has jacked up since Thursday
- concrete pumping arm is missing - this happened sometime last week
- formwork for Basement 4 has nearly surrounded lift core
- eastern part of Podium area Basement 4 has been poured, western part looks ready to pour
- as I write this, a mobile concrete pump is arriving on site, possibly to pour it this afternoon

IMG_20160905_124740.jpg


6 September -
- formwork build continuing around hotel core. I've lost track of what level it's up to!
- formwork going up over the substation area north of the commercial core
- still laying reinforcing & post-tensioning ducts south and east of the commercial core
- Basement 4 formwork platform nearly complete around res core
- last bit of Basement 4 has been poured in the podium area, with Basement 3 formwork spreading

IMG_20160907_134839.jpg




7 September -
- substation area north of commercial core is almost completely covered by formwork
- columns being poured in podium area
- reinforcing being placed around res core

IMG_20160907_134839.jpg


8 September -
Looks like no work today.

IMG_20160908_121630.jpg


9 September -
- pouring columns around hotel core
- basement 1 east & south of commercial core poured this morning (it looks like there's a section that's going to be thicker, that will be poured with the western part)
- still laying reinforcing west of res core
- Basement 4 formwork in the podium area. Worth a look at the plans to figure out what's going on, the various carpark access ramps start getting complicated from here.


-i