300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 12th of September and 16th of September

Here's an update from last week's construction activities. Lots of grids and lots of pouring of concrete! The site is rising up quite quickly.

14 September -
- formwork & reinforcing around the hotel core
- Basement 1 reinforcing being laid in remaining sections
- reinforcing being laid for eaten half of Basement 4 (I think) near res core
- Basement 4/3 carpark ramp poured near southern boundary in podium area
-formwork & reinforcing being laid for Basement 3 in podium area - looks like the middle third is nearly ready to pour.

IMG_20160914_120823.jpg


15 September -
- formwork expanding in hotel area
- reinforcing being laid in commercial area
- eastern half of Basement 4 poured near res core
- Basement 3 formwork nearly finished in podium area, with reinforcing being laid in middle third
- the carpark ramp on the far left (southern edge of site) is the main carpark access ramp, according to the drawings. Over the next couple of levels, this angles across the site to come out on North Quay next to the hotel entrance.

IMG_20160915_123426.jpg




16 September -
- concrete pumping going on since this morning around the hotel core, not sure what they're pouring
- slab over the substation has been poured north of the commercial core
- reinforcing being laid in the podium area
- formwork going up for Basement 3 around the res core


IMG_20160916_090329.jpg IMG_20160916_121459.jpg


-i

Mon Sep 19 17:47:29 2016
Photos, Construction, Day, GuestContribution