300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 19th of September and 23rd of September

Here are updates for the past week. Looks like there were a couple of days of no work due to weather.

19 September -
No work today.
Changes since Friday:
- reinforcing laid around hotel core
- columns poured and more formwork built around res core
- middle part of Basement 3 slab poured in podium area. You can see the beginnings of the carpark access ramp on the far left.

IMG_20160919_142416.jpg


20 September -
- reinforcing and post-tensioning ducts laid around hotel core
- slab poured on west side of commercial core
- formwork build around res core
- reinforcing laid in eastern third of podium area

IMG_20160920_171824.jpg




21 September -
Looks almost identical to yesterday. Nobody working in the rain today.

IMG_20160921_155844.jpg


22 September -
- laying reinforcing and post-tensioning ducts around the hotel core, looks like the slab has been poured in the north west corner
- formwork going up above the substation in the north east corner. I think there is low clearance between the slabs here
- also pouring columns there
- Basement 3 formwork progressing around the res core
- lots of scaffolding and formwork around the fire stair in the podium area, reinforcing being laid in the eastern third