300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 7th of November and 10th of November

Here's an update from Bernard for the current week. It's a bit earlier than usual but I will be going away on an extended vacation as of tonight. I'll try to keep the blog updated when I can, but I am not sure how much Internet access I will have while travelling.

7 November -
- A bit more work done around the commercial core
- you can see where there's going to be a circular void between Podium floors in the middle of the site
- formwork has been removed from part of the carpark access ramp side walls near the res core

IMG_20161107_123500.jpg


8 November -
- pouring a floor slab on the hotel
- looks like recessed beams have been poured west of the commercial core, but the rest of the slab still to do
- assorted columns & walls being prepped around the res core and the podium area

IMG_20161108_125042.jpg


9 November -


- formwork going up for the next hotel floor & supporting columns
- podium 2 level poured west of commercial core
- columns being poured around res core, more carpark ramp formwork going up
- some Basement 1 formwork going up in the podium area next to the crane

IMG_20161109_134401.jpg


10 November -
- formwork & scaffolding being assembled north of the hotel core
- some piping being assembled on the formwork north of the commercial core
- columns being worked on around the res core (some formwork being removed from smaller columns)
- formwork for Basement 1 (?) being built in the podium area

IMG_20161110_120702.jpg


-i

Thu Nov 10 22:44:36 2016
Photos, Construction, Day, GuestContribution