300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
I'm looking for someone to acquire and take over 300george.com. This has been an amazing blogumentary project but I simply do not have the time to keep it going. If you're interested, please email me offers at .
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 21st of November and 25th of November

This was a short update from Bernard. Will be posting a number of update videos tomorrow.

21 November -
- column formwork on the hotel tower
- scaffolding going up along the George St & Ann St frontages of the commercial tower
- Basement 1 formwork still being built around the res tower
- pouring the middle third of Basement 1 in the podium area

IMG_20161122_094231.jpg




24 November -
- slab was poured earlier this week on the south-west of the hotel core
- formwork build funding around commercial core
- commercial core has climbed since Tuesday, I think
- Basement 1 formwork still being built north of the res core, with reinforcing starting to be laid on the south side of the core
- last unpoured parts of Basement 1 in the podium area are having post-tensioning ducts and reinforcing laid

IMG_20161124_115300.jpg


-i

Tue Dec 20 14:51:05 2016
Photos, Construction, Day, GuestContribution