300 George Street Blogumentary
300 George Street
Brisbane, Australia
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to

You can also contact me via the FaceBook page:
300 George Street Brisbane

Recent Posts

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development

Updates between 28th of November and 2nd of December

Still playing catch up with all the updates. These are from Bernard for the 28th of November to the 2nd of December.

28 November -
- formwork for the next floor of the hotel is progressing rapidly
- podium 3 formwork still going up around the commercial core
- most of the formwork for the porte cochere is now in place, north of the res core
- lots of vertical rebars poking up at the locations of various walls east of the res core
- you can see the location of the upper carpark ramp (which I think services the commercial building carpark) cutting across the podium area, just the other side of the nearest crane
- demolition of the loading platform on the Adelaide St frontage has begun!


29 November -
- still building formwork north of the hotel core
- you can see the formwork shutter in the pink cage has been jacked back away from the poured wall
- formwork being built around the commercial core
- reinforcing going in South-west of the res core
- still finishing the Basement 1 formwork north of the res core
- the small section that stuck out from the Adelaide St loading platform has been completely removed


30 November -
- formwork edge with the wavy profile clearly visible north of the hotel core
- some pretty big cast-in beams between the hotel and commercial cores, judging by the areas with the post-tensioning ducts laid
- still laying reinforcing around the res core for Basement 1
- some scaffolding going up in the podium area, otherwise it just looks like a stockpile area at the moment


1 December -
- setting up reinforcing for columns around the hotel core
- more reinforcing and PT ducts being laid between the hotel and commercial buildings
- scaffolding starting to go up over the commercial foyer area in the northeast corner
- laying reinforcing around the res tower