300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you want to get in touch, please email me on
.


Recent Posts

Final update for 300 George Street

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 30th of January and 3rd of February

Another update from Bernard for the past week. Enjoy!

30 January -
- more reinforcing placed on the hotel tower. That slab is going to be pretty strong!
- formwork build continuing between hotel and commercial cores
- more scaffolding going up around the NE corner, near George & Ann Sts
- you can clearly see the building outline in the SE corner (George & Adelaide corner)

IMG_20170130_093717.jpg


31 January -
- P-T ducts being added to the hotel tower. Curious wave pattern!
- formwork & reinforcing between the hotel & commercial cores
- formwork going up in SW corner near res core
- pouring columns NE of res core
- still laying out formwork for building entrance in podium area, facing George/Adelaide streets

IMG_20170131_154720.jpg




1 February -
- still adding reinforcing and post-tensioning ducts to that massive slab on the hotel tower
- formwork and reinforcing being built west of the commercial core
- lots of assorted formwork around the res core
- supports are going up for the carpark ramp that opens on to Adelaide St just north of the loading platform
- slab has been poured this morning in the SE corner

IMG_20170201_134326.jpg


3 February -
- lots more P-T ducts on the hotel tower
- reinforcing and P-T ducts between the hotel and commercial towers
- formwork expanding north of the commercial core
- perimeter scaffolding at NE corner building up
- formwork build continuing around res core and in podium area

IMG_20170203_121227.jpg


-i

Sat Feb 4 15:35:44 2017
Photos, Construction, Day, GuestContribution