300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 20th of March and 24th of March

Another great update from Bernard. The building outline is very clear now.

22 March -
- formwork has covered the hotel tower, ready for the next floor slab
- scaffolding and formwork spreading over the commercial tower
- the western portion of the podium slab has been poured

Pretty wet the past few days, I'm surprised they've made this much progress!

IMG_20170322_171326.jpg


23 March -
- slab poured on Western side of hotel tower, reinforcing being laid for northern part
- formwork spreading over commercial tower area, with set downs for cast in beams visible
- formwork covering north and east of res core. Floor slabs visible at different levels near hotel core
- formwork for next podium area slab being constructed

IMG_20170323_153600.jpg




24 March -
- formwork for walls up to SW of hotel core. Can't see, but a pour of these may be underway
- reinforcing looks ready to pour N of hotel core
- formwork has covered most area N of commercial core, reinforcing being laid
- more formwork under construction in Podium area

IMG_20170324_134755.jpg


-i

Mon Mar 27 14:36:47 2017
Photos, Construction, Day, GuestContribution