300 George Street Blogumentary


This blog is following the construction and development of the building complex planned for 300 George Street. It is in no way affiliated with the developer of this site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
. Please like it too!

ExpressWayCam.com ExpressWayCam.com

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Recent Posts

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane

Time lapses for the whole month of March all in one go

Updates between 29th of May and 2nd of June

Catching up on time lapse videos for February 2017

Updates between 22nd of May and 26th of May, plus a bonus ground level photo

Time lapse of the site between 3rd of February and 10th of February 2017

Fog blankets the site

Updates between 8th of May and 19th of May

Hotel tower soars above Quay Central building

Updates between 1st of May and 5th of May

Updates between 24th of April and 28th of April

Time lapse of the site between 27th of January and 3rd of February 2017

A slow week around Easter

New renders of the W Hotel and 300 George Site

Updates between 10th of April and 14th of April

Foggy Brisbane morning

Updates between 3rd of April and 7th of April

Updates between 27th of March and 31st of March


RSS Feed

Top Categories


Updates between 3rd of April and 7th of April

9-Apr-2017

A short but excellent update from Bernard for the past week, enjoy!

4 April -
- next floor of formwork has been erected on the hotel tower
- slab north of commercial core has been poured
- prep nearly done for slab southeast of res core, looks like the formwork has covered the rest of the area West of the res core
- reinforcing starting to go down in the eastern half of the podium slab

IMG_20170404_120620.jpg


6 April -
- pouring another floor slab on the hotel
- formwork build east of commercial core
- reinforcing being laid west of res core
- reinforcing and post-tensioning ducts being laid in eastern half of podium area

IMG_20170406_120607.jpg




7 April -
- slab ready to pour north of hotel core
- formwork build continuing east of commercial core
- reinforcing still being laid on west side of res core
- reinforcing mesh sheets being laid in eastern half of Podium area

IMG_20170407_121419.jpg


-i

Time: Sun Apr 9 16:56:50 2017
Tags: [ Photos, Construction, Day, GuestContribution ]