300 George Street Blogumentary


This blog is following the construction and development of the building complex planned for 300 George Street. It is in no way affiliated with the developer of this site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
. Please like it too!

ExpressWayCam.com ExpressWayCam.com

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Recent Posts

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane

Time lapses for the whole month of March all in one go

Updates between 29th of May and 2nd of June

Catching up on time lapse videos for February 2017

Updates between 22nd of May and 26th of May, plus a bonus ground level photo

Time lapse of the site between 3rd of February and 10th of February 2017

Fog blankets the site

Updates between 8th of May and 19th of May

Hotel tower soars above Quay Central building

Updates between 1st of May and 5th of May

Updates between 24th of April and 28th of April

Time lapse of the site between 27th of January and 3rd of February 2017

A slow week around Easter

New renders of the W Hotel and 300 George Site

Updates between 10th of April and 14th of April

Foggy Brisbane morning

Updates between 3rd of April and 7th of April

Updates between 27th of March and 31st of March


RSS Feed

Top Categories


Updates between 8th of May and 19th of May

21-May-2017

This is a combined update from Bernard for the past two weeks, since there was little activity the week earlier.

9 May -
- another day, another floor on the hotel… :-) Currently doing the fourth floor above that thick slab
- some very tall columns have been poured for the commercial tower! Scaffolding going up to support the slab formwork
- pouring the slab East of the res tower, formwork nearly finished for the west half
- formwork being built for the podium area. Looks like a complicated slab, with some pretty deep cast-in beams. This may be the last slab pour for the podium area.

IMG_20170509_140701.jpg


15 May -
- reinforcing being laid atop the hotel tower. Now on the 5th level above the transition slab
- formwork being laid on the scaffolding north of the commercial core
- post-tensioning ducts being laid west of the res core
- formwork build continuing in the podium area. Looks like those cast-in beams are going to be very deep.

IMG_20170515_133122.jpg




Here's a picture of the glass curtain wall being put up.
IMG_20170516_092113.jpg


17 May -
- formwork already going up for next floor at SW of hotel, looks ready to pour to north
- pouring hotel core
- scaffolding and formwork expanding over north side of commercial tower
- pouring slab on west side of res core
- still building formwork in podium area, with post-tensioning ducts being laid in eastern part. Looks like there might be a significant height difference between parts of this slab.

IMG_20170517_125736.jpg


-i

Time: Sun May 21 23:31:57 2017
Tags: [ Photos, Construction, Day, GuestContribution ]