300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
I'm looking for someone to acquire and take over 300george.com. This has been an amazing blogumentary project but I simply do not have the time to keep it going. If you're interested, please email me offers at .
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 29th of May and 2nd of June

Here's an update from Bernard for the past week, enjoy!

30 May -
- floor has been poured and formwork going up for the next four on the hotel tower
- reinforcing and post-tensioning ducts being laid for NE part of commercial tower
- formwork starting to cover the area around the res core for what I think is the last podium level
- reinforcing being laid for the podium area

IMG_20170530_123847.jpg


31 May -
- formwork for the next floor on the hotel is nearly complete
- the NE corner of the commercial tower looks just about ready to pour concrete
- formwork build continuing around the res core
- western half of the podium area looks ready to pour concrete

IMG_20170531_120110.jpg




2 June -
- reinforcing place on the hotel tower, looks almost ready to pour
- NE corner of the office tower has been poured
- formwork slowly expanding around res core
- western half of podium area has been poured since Wednesday

IMG_20170602_170248.jpg


-i

Tue Jun 6 23:32:36 2017
Photos, Construction, Day, GuestContribution