300 George Street Blogumentary


This blog is following the construction and development of the building complex planned for 300 George Street. It is in no way affiliated with the developer of this site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
. Please like it too!

ExpressWayCam.com ExpressWayCam.com

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Recent Posts

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane

Time lapses for the whole month of March all in one go

Updates between 29th of May and 2nd of June

Catching up on time lapse videos for February 2017

Updates between 22nd of May and 26th of May, plus a bonus ground level photo

Time lapse of the site between 3rd of February and 10th of February 2017

Fog blankets the site

Updates between 8th of May and 19th of May

Hotel tower soars above Quay Central building

Updates between 1st of May and 5th of May

Updates between 24th of April and 28th of April

Time lapse of the site between 27th of January and 3rd of February 2017

A slow week around Easter

New renders of the W Hotel and 300 George Site

Updates between 10th of April and 14th of April

Foggy Brisbane morning

Updates between 3rd of April and 7th of April

Updates between 27th of March and 31st of March


RSS Feed

Top Categories


Updates between 12th of June and 16th of June

19-Jun-2017

It was a wet week but work still went on. Here's an update from Bernard, including an updated shot of the wavy glass facade for the W Hotel.

13 June -
A wet day on the site…

- slab poured on SW of hotel, reo ready to pour the N part
- still not much visible action on the commercial tower
- reinforcing being laid for W half of slab around res core, looks ready to pour the E half
- the rest of the slab has been poured in the podium area

IMG_20170613_162713.jpg


14 June -
- formwork in place for walls on SW of hotel, with reo looking ready to go on N
- pouring another level of the commercial core
- not much else going on today. Pretty wet out.

IMG_20170614_114441.jpg




15 June -
- N side of hotel tower has been poured this morning
- reinforcing still being laid around the res core
- some formwork walls going up between the podium area and the commercial core. This large rectangular area sits across the three large columns on lower levels, so perhaps a large load transfer​ beam

IMG_20170615_130554.jpg


16 June -
- formwork going up for the next four on the hotel tower. Getting pretty tall, now
- pouring the slab eat of the res core
- laying reinforcing W of res core
- building a heavily reinforced cage where that box formwork is just S of the commercial core

IMG_20170616_114559.jpg


The glass facade is getting bigger…
IMG_20170614_084834.jpg


-i

Time: Mon Jun 19 15:43:04 2017
Tags: [ Photos, Construction, Day, GuestContribution ]