300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter

Updates between 3rd of July and 7th of July

Scaffolding removed around the commercial tower

Updates from different angles, plus a video of the work on top of the W hotel tower

Updates between 26th of June and 30th of June

Updates between 19th of June and 23rd of June

Multiplex Appointed To Build Brisbane Quarter Commercial Tower

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane

Time lapses for the whole month of March all in one go

Updates between 29th of May and 2nd of June

Catching up on time lapse videos for February 2017

Updates between 22nd of May and 26th of May, plus a bonus ground level photo

Time lapse of the site between 3rd of February and 10th of February 2017


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 26th of June and 30th of June

Another excellent update from Bernard for the past week. Not a full working week on site, but weekend work continues.

26 June -
No work on site today.
- reinforcing placed on SW side of hotel, formwork build on N
- reinforcing and post-tensioning ducts still being laid W of res core
- you can see, just left of the res core, an area with no reinforcing, with a compressor sitting in it. I think that's where the pool for the res tower goes.

IMG_20170626_150249.jpg


27 June -
- SW slab on hotel tower poured, formwork complete on N side, reinforcing starting to be laid
- the hotel tower has nearly another 20 floors to go!
- more reinforcing being placed in the formwork for that massive beam S of the commercial core
- pouring the slab W of the res core

IMG_20170627_122101.jpg




28 June -
- reinforcing being laid on hotel tower
- formwork being built for a raised section of slab around the res core
- column reinforcing cages being placed around res core

I think the 'roof' of the podium building is now complete, so we'll only see the towers climb up any higher. I'm wondering when they'll pour the southern part of the commercial building floors - probably when they finish whatever it is they're doing with that massive concrete beam.

IMG_20170628_121045.jpg


29 June -
- N slab poured on hotel, formwork going up on SW
- more reinforcing being built (a very dense cage!) in that box beam formwork S of the commercial core
- scaffolding starting to go up around the E side of the res tower footprint!