300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 3rd of July and 7th of July

Huge update for last week from Bernard! Different angle on photos too so that everything can be fit in. The W Hotel tower is getting big!

3 July -
- raising the safety cages and laying reinforcing on the hotel tower
- pouring the next stage of the massive beam S of the commercial core
- formwork being installed for the parapet wall S of the res core

IMG_20170703_120807.jpg


4 July -
- pouring the hotel core
- slab poured on SW of hotel, reinforcing being laid on N
- looks like commercial tower footprint S of core has been tidied up - possibly in preparation for scaffolding & formwork for the slab sections to catch up with the N side
- columns being poured around the res core

I think the crane in the NW corner near the hotel will have to jack up again soon.
Also looks like a couple of truckloads of metal racks with more windows for the hotel facade have turned up - you can see one of the trucks in the southern loading dock in the photo.

IMG_20170704_121029.jpg


5 July -
- formwork for the next level on the SW of the hotel, looks nearly ready to pour the N side
- formwork supports going up S of the commercial core
- with the formwork shutters removed, it looks like that solid concrete 'beam' is 5-6 metres thick!
- more scaffolding going up around res tower, with columns being poured

IMG_20170705_153434.jpg




6 July -
- pouring N side of hotel, formwork going up for SW side
- formwork supports continuing to go up S of commercial core
- more scaffolding around the res tower footprint
- some scaffolding being removed from SE corner of podium area

IMG_20170706_103653.jpg


7 July -
A bit wet out today, not much work visible right now.
- formwork done, reinforcing being placed SW side of hotel tower
- formwork supports gradually filling the space S of the commercial core
- the outline of the res tower is fairly well defined by scaffolding right now

IMG_20170707_120719.jpg


-i

Tue Jul 11 15:49:52 2017
Photos, Construction, Day, GuestContribution