300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter

Updates between 3rd of July and 7th of July

Scaffolding removed around the commercial tower

Updates from different angles, plus a video of the work on top of the W hotel tower

Updates between 26th of June and 30th of June

Updates between 19th of June and 23rd of June

Multiplex Appointed To Build Brisbane Quarter Commercial Tower

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 17th of July and 21st of July

Here's an update from Bernard for the past week.

17 July -
I'm not sure there's been any work going on today. Doesn't look like anyone's there now.

IMG_20170717_154716.jpg


18 July -
- formwork build on hotel tower
- pouring blade walls on the N side using a crane bucket
- continuing to dismantle climbing formwork on office core
- formwork supports starting to go up for the first slab of the res tower

IMG_20170718_150343.jpg


19 July -
- SW slab poured on hotel, reinforcing starting to be laid on N side
- the jacking formwork on the office core is still being dismantled. The parts seem to be stacked around the place, so I have no idea why this is happening. I guess we'll find out!
- formwork starting to cover area SE of res core

IMG_20170719_133836.jpg




20 July -
- pouring the hotel core
- reinforcing starting to be laid S of the office core
- formwork for the res tower expanding

IMG_20170720_133636.jpg


21 July -
- the hotel core has jacked up another level, I can see Level 25 below the formwork. Those numbers will make it easy to see which floor they're up to!
- formwork for L22 SW, reinforcing for L21 N
- more dismantling of the jacking frame on the office core
- reinforcing still being laid S of the office core
- formwork for the first Res tower floor nearly complete
- more scaffolding has been removed from the SE corner
- from street level you can see insulation and fire sprinkler systems being installed below the concrete slabs

IMG_20170721_135507.jpg