300 George Street Blogumentary
300 George Street
Brisbane, Australia
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to

You can also contact me via the FaceBook page:
300 George Street Brisbane

Recent Posts

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development

Updates between 17th of July and 21st of July

Here's an update from Bernard for the past week.

17 July -
I'm not sure there's been any work going on today. Doesn't look like anyone's there now.


18 July -
- formwork build on hotel tower
- pouring blade walls on the N side using a crane bucket
- continuing to dismantle climbing formwork on office core
- formwork supports starting to go up for the first slab of the res tower


19 July -
- SW slab poured on hotel, reinforcing starting to be laid on N side
- the jacking formwork on the office core is still being dismantled. The parts seem to be stacked around the place, so I have no idea why this is happening. I guess we'll find out!
- formwork starting to cover area SE of res core


20 July -
- pouring the hotel core
- reinforcing starting to be laid S of the office core
- formwork for the res tower expanding


21 July -
- the hotel core has jacked up another level, I can see Level 25 below the formwork. Those numbers will make it easy to see which floor they're up to!
- formwork for L22 SW, reinforcing for L21 N
- more dismantling of the jacking frame on the office core
- reinforcing still being laid S of the office core
- formwork for the first Res tower floor nearly complete
- more scaffolding has been removed from the SE corner
- from street level you can see insulation and fire sprinkler systems being installed below the concrete slabs