300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 31st of July and 4th of August

31 July -
- hotel core now showing Level 26
- L23 slab formwork on SW side, starting to build forms for blade columns for L22 to N
- reinforcing and post-tensioning ducts being laid to S side of office tower
- still laying reinforcing and post-tensioning ducts to NW side of res tower

IMG_20170731_133302.jpg


1 August -
- building L23 formwork for the hotel
- still laying reinforcing & post-tensioning ducts for the office tower
- putting some walls below the slab level just south of the office core
- the NW side of the res tower slab has been poured

IMG_20170801_153627.jpg




2 August -
- reinforcing laid SW side of hotel, formwork on N
- continuing to lay reinforcing S of office core
- pouring the res core

IMG_20170802_120134.jpg


4 August -
- formwork for L24 going up SW side of hotel, reinforcing for L23 on N
- pouring slab S of office core
- scaffolding might be starting to go up around the next level of the res tower