300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 7th of August and 11th of August

Here's another update from Bernard for the last week.

7 August -
- L24 on hotel: reinforcing being laid to SW, formwork to N
- hotel core has jacked up to reveal L27
- more scaffolding going up around the S side of the office tower

IMG_20170807_121732.jpg


8 August -
- hotel L24: reinforcing being laid to SW, formwork looks done to N
- office: scaffolding around S side
- res: not much visible happening
- lots of what looks like formwork shutters in the podium area, no idea what they're for

IMG_20170808_132129.jpg


9 August -
- hotel: nearly finished laying reinforcing SW of L24, starting on N
- office: still scaffolding the S perimeter, some large metal cages being craned over, no idea what they are
- res: not much visible up top
- materials (pipes, insulation, etc) being craned in to loading platforms that extend from SE corner of podium area. This will be for the continuing internal fitout of the lower floors (some of this is visible from the street)

IMG_20170809_135535.jpg




10 August -
- hotel: SW of L24 poured, reinforcing being laid to N, pouring lift core
- office: formwork being installed around stairs just S of the lift core, perimeter scaffolding looks complete
- res: some work atop lift core, formwork has been removed from skylight between trees and hotel towers, being used as an access hatch to crane out formwork supports from lower level