300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 14th of August and 18th of August

A grea update from Bernard for the past week. Some days off due to Ekka holiday.

14 August -
- hotel: L28 visible on lift core, forming up L25 to SW, L24 has been poured to N
- office: formwork supports going up for southern slab. Not sure how high this one will be, possibly a mezzanine floor, rather than to the same height as the N side of the building (which seems to be double height between the topmost slab that has been poured and the one below)
- res: a lot of the cladding around the climbing formwork on the lift core has been removed. It'll be worth checking the drawings to see if the lift core changes shape at this height

IMG_20170814_135021.jpg


15 August -
Looks like the site is closed today, maybe an extra Ekka holiday for them?


17 August -
- hotel: L25 formwork built to SW, forms for L24 columns being built to N
- office: not much visible progress since last photo. Part of the scaffolding has been removed on the S side, and there's a boom lift, but I can't see what's happening
- res: work with the climbing formwork on the lift core ongoing. Scaffolding being removed from the perimeter
- several crane tower segments are sitting in the podium area, ready to raise one of the cranes
- In this street level shot you can see that they're removing the formwork shutters from the res core. Maybe different ones are going to be used due to different floor spacing?


IMG_20170817_120954.jpg IMG_20170817_122411.jpg




18 August -
- hotel: reinforcing laid for L25 SW side, formwork up for N side
- office: no visible change
- res: all the formwork shutters have been removed from the res core, the SE end of the first tower slab has been exposed
- it also looks like a new crane support frame has been positioned on top of the podium area. I assume this will serve as a base for the crane currently just beside it, which will allow the holes in the basement & podium slabs to be filled and the fitout of those levels completed while the office tower is being built

IMG_20170818_120842.jpg


Finally here's a great photo from the Victoria Bridge side…
IMG_20170814_093252.jpg


-i

Tue Aug 22 13:46:59 2017
Photos, Construction, Day, GuestContribution