300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 21st of August and 25th of August

Another great update from Bernard. A crane has been partially disassembled this week and more weekend work goes on, even on Sundays.

21 August -
- hotel: L25 SW slab poured, N reinforcing being laid. Pouring the lift core.
- office: more formwork supports going up for S slab
- res: more of the climbing formwork has been removed
- the crane in the podium area has been relocated to the black support frame, as expected. Well, the tower has, the actual crane from the top is nowhere to be found!
- Showing both the old and new crane towers. Can't see in this photo, but there are some large black metal beams under the concrete slab, where the new crane support frame is bolted through.


IMG_20170821_120458.jpg IMG_20170821_124205.jpg


22 August -
- hotel: L25 forms for blade columns going up to SW, reinforcing for slab to N
- office: still building formwork supports to S of core
- res: new parts for the climbing formwork arriving, I think (being piled up SE of the lift core
- no additional construction of the crane in the podium area

IMG_20170822_115200.jpg


23 August -
- hotel: L25 North has been poured, formwork going up for L26 SW
- office: not much change since yesterday
- res: dismantling of the climbing formwork on the core continues

IMG_20170823_122133.jpg




24 August -
Thunderstorms!

- hotel: L29 visible on the core. Formwork build for L26 continuing. Rails for work platforms to fit wall cladding being installed.
- office: formwork laid E of core, not much visible progress elsewhere
- res: more of the climbing formwork removed. I think, looking at the plans (Plans6.pdf, from p.10), this is being reconfigured to include poured walls between the core and some of the large columns near the edge of the tower (you can see some reinforcing poking up from the slab both NE & SW of the core)

IMG_20170824_152024.jpg


-i

Mon Aug 28 15:40:04 2017
Photos, Construction, Day, GuestContribution