300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 4th of September and 8th of September

Here's an update from Bernard for the past week.

4 September -
- hotel: L27 looks ready for pouring to the N, forms for columns going up to SW
- office: slab E of lift core looks like it was poured on the weekend, reinforcing still being placed S of core
- res tower looks pretty bare right now

IMG_20170904_131420.jpg


5 September -
- hotel: L27 North poured, formwork going up for L28 SW side
- office: still building wall reinforcing S of the lift core. Some additional cages being installed below the climbing formwork
- res: nothing visible

IMG_20170905_121519.jpg


6 September -
- hotel: formwork has jacked up, revealing L31; formwork build for L28 underway; gantry on E side installing mount points for cladding system (likely to be aluminium composite panels, presumably non-flammable type!)
- office: still working on walls S of core. Cage below jacking formwork on core still being built

IMG_20170906_122519.jpg




8 September -
- hotel: reinforcing being laid for L28; part of the E side concrete has been painted - maybe they're not going to clad it?
- office: looks like some of the plant room walls S of the core have been poured, forms being placed for pouring a large wall on the building edge (this will be sitting on the large concrete beam built down lower)

IMG_20170908_120345.jpg