300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you want to get in touch, please email me on
.


Recent Posts

Final update for 300 George Street

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 4th of September and 8th of September

Here's an update from Bernard for the past week.

4 September -
- hotel: L27 looks ready for pouring to the N, forms for columns going up to SW
- office: slab E of lift core looks like it was poured on the weekend, reinforcing still being placed S of core
- res tower looks pretty bare right now

IMG_20170904_131420.jpg


5 September -
- hotel: L27 North poured, formwork going up for L28 SW side
- office: still building wall reinforcing S of the lift core. Some additional cages being installed below the climbing formwork
- res: nothing visible

IMG_20170905_121519.jpg


6 September -
- hotel: formwork has jacked up, revealing L31; formwork build for L28 underway; gantry on E side installing mount points for cladding system (likely to be aluminium composite panels, presumably non-flammable type!)
- office: still working on walls S of core. Cage below jacking formwork on core still being built

IMG_20170906_122519.jpg




8 September -
- hotel: reinforcing being laid for L28; part of the E side concrete has been painted - maybe they're not going to clad it?
- office: looks like some of the plant room walls S of the core have been poured, forms being placed for pouring a large wall on the building edge (this will be sitting on the large concrete beam built down lower)

IMG_20170908_120345.jpg