This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels

Time lapse videos for all of May

George Street closed off on the weekend with a mobile crane

Updates between 21st of August and 25th of August

Updates between 14th of August and 18th of August

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 2nd of October and 6th of October

A short update from Bernard for the past week…

3 October -
- hotel: L34 just peeking out from under the climbing form. This may be as high as this goes. Glazing complete on North (Ann St) facade up to L23. Looks like the concrete walls facing into the site are just being painted, no cladding.
- office: more scaffolding and formwork S of the lift core than two weeks ago, but not much other progress visible, apart from the safety fencing going up around the perimeter that will climb with the main floor plate construction.
- res: no obvious changes over the last fortnight
- I notice a 'lid' has been placed over the large skylight opening between the hotel & res towers to keep the weather out.


IMG_20171003_085004.jpg IMG_20171003_120222.jpg




6 October -
- hotel: L31 slab poured to SW, reinforcing being laid to N. Looks like cladding prep to E facing walls.
- office: work on section S of lift core. Appears to be parts of climbing formwork on the slab N of the core, not sure where this is going - perhaps on the southern part of the core?
- still no work on the res tower

IMG_20171006_120838.jpg


-i

Mon Oct 9 16:02:45 2017
Photos, Construction, Day, GuestContribution