300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 9th of October and 13th of October

Here's an update from Bernard for the past week…

9 October -
Well, the mystery of the extra climbing formwork sections has been solved - it looks like the southern wall of the office tower will be a poured-in-place structural concrete wall.

- Hotel: L31 formwork & reinforcing. More cladding mounting brackets attached to E wall
- Office: climbing formwork constructed on S wall, formwork & reinforcing for walls S of lift core.
- Res: more materials stockpiled on slab, but no obvious progress
- pedestrian walkway has been removed from SE corner, and looks like the ground level slab is done there (part of it is black?)

IMG_20171009_143024.jpg


11 October -
- hotel: L31 precast walls up, formwork going up for L32
- office: formwork still being installed S of core
- soil for garden being placed at corner of Adelaide & North Quay. Lots of the exterior concrete face have been painted black in that area

IMG_20171011_123935.jpg




13 October -
- hotel: pouring L32 support walls to N. Can no longer see what stage they're at to SW, it's above my height.
- office: concrete walls S of core have been poured this morning. Installing reinforcing for wall along S edge.
- still adding soil to garden bed at SW corner

IMG_20171013_120048.jpg

Walls starting to be constructed on the podium levels.

IMG_20171013_121740.jpg