300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
300 George Street
Brisbane, Australia
Blogumentary
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October

Updates between 9th of October and 13th of October

October fog blankets the site

Updates between 2nd of October and 6th of October

Riverfire 2017 photos - jets, helicopters and fireworks

Painting around the lower levels and hotel sides plus number 33 on the hotel core

Updates between 11th of September and 15th of September

News and gossip from the site

Updates between 4th of September and 8th of September

Updates between 28th of August and 1st of September

The W Hotel tower reaches the big 30 levels


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 23rd of October and 3rd of November

Here are some updates from Bernard for two weeks back. Enjoy!

23 October -
- hotel: reinforcing being laid for L32 North. Mounting brackets for wall cladding being fitted. Concrete pour for part of the core in progress (this must be close to the last pour for the hotel core)
- office: assembling climbing formwork on the southern part of the lift core (I believe this will eventually extend over to the southern wall)
- concrete has been removed from the Adelaide St loading platform, steel beams remain

IMG_20171024_115835.jpg


26 October -
- hotel: looks like L32 slabs have been poured. Core formwork has jacked up a little higher than it was a week or so back (about half a floor height), but I don't know when that happened.
- office: scaffolding and formwork South of the core is now well above the slab, approaching the rest of the core.
- res: no work
- steel support beams for the Adelaide St loading platform are being removed

IMG_20171026_132412.jpg




2 November -
- hotel: dismantling of climbing formwork on core has begun. Formwork for L33 being placed. Glazing up to L26, wall cladding brackets up to L22.
- office: formwork shutters being removed from walls South of core
- Adelaide St loading platform structure completely removed. Area at SW corner looks like it's been paved.

IMG_20171102_153105.jpg


-i

Sun Nov 12 17:54:44 2017
Photos, Construction, Day, GuestContribution