This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
300 George Street Brisbane is the site for Brisbane Quarter and W Hotel, Brisbane.
This blog is in no way affiliated with the developer, leasing agents or any businesses planned to operate at 300 George Street Brisbane.

If you want to get in touch, please email me on
.


Recent Posts

Final update for 300 George Street

August 2018 Updates

July 2018 Updates

June 2018 Updates

May 2018 Updates

April 2018 Updates

March 2018 Updates

February 2018 Updates

January 2018 Updates

December 2017 updates

Remaining photos and updates for November 2017

Some cool shots from up high

Links to past time lapse videos

Reducing the frequency of updates and content on this Blog

Updates between 20th of November and 24th of November

Updates between 13th of November and 17th of November

Updates between 6th of November and 10th of November

Updates between 23rd of October and 3rd of November

A new crane installed at the commercial building site

Updates between 16th of October and 20th of October


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

July 2018 Updates

There has been some solid, visible progress on the residential tower in July. The W Hotel is old news now and the commercial tower is climbing higher and higher. It's interesting to see that the commercial tower windows are being placed as it is built up, unlike what happened with W Hotel where windows were installed significantly later. There was a police presence on the site one of the days too, though I am not sure why.

Here's an update from a source on site…
- Residential Tower is under construction
- 82 level residential tower with 2 pools and recreational areas.
- The completion is planned in October 2021.
- There are significant challenges in relation to aviation safety, but there is a plan in place for this.
- The sales suite is being constructed at the moment and is located in the retail tenancy on level 1 and 2 on the corner of George and Adelaide (within the retail tenancy).
- It is a whole building jump lending to faster construction.


DSC04278.JPG DSC04521.JPG

IMG_0931.jpg IMG_0932.jpg IMG_0933.jpg

IMG_0934.jpg IMG_0935.jpg IMG_0936.jpg




Here's an update from Bernard…
4 July -

- a crane has been erected on the residential tower, and a column reinforcing cage had been placed
- the cranes for the office tower have climbed again, now above my level, as is the top of the climbing formwork
- glazing installation to the office tower is proceeding pretty rapidly

10 July -

Office tower
- slab poured this morning
- reinforcing being laid for the next piece
- new steel columns will need to be installed for the next floors
Res tower
- formwork being installed for several columns & walls
- reinforcing cages in place for most of the large columns

25 July -

- formwork being laid for another office floor
- South wall concrete pour underway
- plenty of glazing already installed to the office tower, some cladding prep being done to the lower part of the South wall
- reinforcing and post-tensioning ducts being laid in preparation for a floor slab pour on the res tower

26 July -

- slab poured on res tower
- office core formwork jacking up again

31 July -

Office:
- slab poured this morning on SE corner
- formwork going up quickly for the next floor
Res:
- formwork & reinforcing going up for columns & structural walls for the next level

00001IMG_00001_BURST20180726120740_COVER.jpg

PANO_20180704_134504.jpg PANO_20180710_122656.jpg PANO_20180731_120927.jpg


-i

Sun Aug 12 14:53:46 2018
News, Photos, Construction, Day, GuestContribution