300 George Street Blogumentary


This blog is following the construction and development of the building complex planned for 300 George Street. It is in no way affiliated with the developer of this site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
. Please like it too!

ExpressWayCam.com ExpressWayCam.com

Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Recent Posts

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane

Time lapses for the whole month of March all in one go

Updates between 29th of May and 2nd of June

Catching up on time lapse videos for February 2017

Updates between 22nd of May and 26th of May, plus a bonus ground level photo

Time lapse of the site between 3rd of February and 10th of February 2017

Fog blankets the site

Updates between 8th of May and 19th of May

Hotel tower soars above Quay Central building

Updates between 1st of May and 5th of May

Updates between 24th of April and 28th of April

Time lapse of the site between 27th of January and 3rd of February 2017

A slow week around Easter

New renders of the W Hotel and 300 George Site

Updates between 10th of April and 14th of April

Foggy Brisbane morning

Updates between 3rd of April and 7th of April

Updates between 27th of March and 31st of March


RSS Feed

Top Categories


01-Aug-2016
Updates between 25th of July and 29th of July
Quite a big update for the past week from Bernard. Check out how high the NW crane reaches now in the pictures for the 28th of July. It's still not over the height of the 'Quay Central' building but is not far off!
05-Mar-2016
Time lapse of the site between 19th and 26th February 2016
Here's another time lapse video from Bernard showing the site between the 19th and 26th of Feburary. This video has footage of the fourth crane being assembled. Its easy to miss but if you look at around the 0:33 mark you will see it, it's fully assembled by the 0:45 mark.
29-Feb-2016
The fourth crane has been assembled on site
Some great developments last week. The fourth crane is now assembled and a service elevator has been put up next to the hotel lift core. The progress has really accelerated. Check out more detailed updates from Bernard below...
30-Jan-2016
A flood of updates this week, including DA changes to the site
There has been a flood of updates towards the end of the week with photos and information sent in by long time readers Geoff, Bernard and Steve. One of the things I missed earlier this month is that there is a Slight Update for 300 George Street & W Hotel DA. On the most part it looks like the number of larger units was decreased in favour of two bedroom apartments. Additional roofing has been added and car parking spaces have been increased.
20-Jan-2016
More concrete, more crane sections, more progress
Thanks again to Bernard for sending this update in. The vantage point in this photo is really quite amazing and the progress is very visible from day to day now.
17-Jan-2016
More concrete being poured in
I've got another update from Bernard a couple of days ago but didn't have time to put it up until now. You can definitely see the progress in this new photo that he's sent in. There are new floor slabs that have been poured in place and more.
14-Jan-2016
Another amazing aerial shot of the site and an update on the construction
Here's another photo from Bernard, it's an update on the previous aerial shot he's sent in. Rather than me paraphrasing what he said, here's a nice summary directly from him...
15-Dec-2015
More of the lift shafts are starting to pop up
I've received quite a detailed update from Bernard, a reader who has contributed in the past. Lots of work is going ahead at the site. It's great to see the site from this vantage point, really puts it into perspective. Many thanks for this contribution!
07-Dec-2015
Third crane assembled on site now
I've noticed this Saturday that more crane parts were delivered to the site. The road wasn't blocked off like the previous two times, that's because this crane was assembled in the center of the site.
09-Nov-2015
Second crane up on the George Street side of the site
A part of George Street was blocked of on Sunday while workers assembled the second crane. Here are some pictures I took while walking past.
06-Nov-2015
Night time works with a mobile crane, North Quay blocked off
Not sure what was going on exactly last night, but there was a mobile crane blocking off North Quay. I was hoping it would be assembling a new crane onsite, but sadly that was not the case. For a long time the mobile crane just stood there with lights off all around, it was gone by 3am.
20-Oct-2015
North Quay was blocked this weekend while a crane was put together
North Quay was blocked over the weekend while the construction crew put together the first crane at the construction site.