300 George Street Blogumentary
HomeDemolitionExcavationConstructionTrouble
This is a blogumentatry project that is following the construction and development of the building complex planned for 300 George Street, Brisbane, with the aim of capturing the history from demolition of the old court building to the final completion of the three new towers.
This blog is in no way affiliated with the developer of the building site.

If you have photos or news to submit, please email them to
.

You can also contact me via the FaceBook page:
300 George Street Brisbane
.


Recent Posts

Updates between 7th of August and 11th of August

Updates between 31st of July and 4th of August

Time lapse videos for all of April

W Hotel curved window installation

Updates between 24th of July and 28th of July

Updates between 17th of July and 21st of July

North Quay crane extended, new number 25 painted on the elevator shaft

Updates between 10th of July and 14th of July

Night time construction zoom in fun

Close up photos of work on the W Hotel tower

Photos from around the site perimeter

Updates between 3rd of July and 7th of July

Scaffolding removed around the commercial tower

Updates from different angles, plus a video of the work on top of the W hotel tower

Updates between 26th of June and 30th of June

Updates between 19th of June and 23rd of June

Multiplex Appointed To Build Brisbane Quarter Commercial Tower

Updates between 12th of June and 16th of June

Updates between 5th of June and 10th of June

Cranes shooting rainbows over Brisbane


Official Pages

300 George Brisbane
Brisbane Quarter
Brookfield Multiplex
Brisbane Development
Wikipedia

Updates between 24th of July and 28th of July

Here's the update for the past week, from Bernard.

24 July -
Showing the insulation and services (fire, stormwater) being fitted below the top slab, which is the roof of the podium area.

The darker patches along the edge of the slabs is grout filling in the boxes where the post-tensioning cables are tightened & anchored.

IMG_20170724_090536.jpg

- L22 formwork mostly complete on SW, blade wall forms being assembled to N
- the office core mystery is solved! The climbing formwork is being shrunk, as the southernmost bank of lifts only service the podium floors, not the highrise tower (I could have probably figured that out last week if I'd remembered to look at the drawings!)
- still laying reinforcing S of the office core
- starting to lay reinforcing for the res tower slab

IMG_20170724_120230.jpg


Continue reading…  

Tue Aug 1 15:08:53 2017
Photos, Construction, Day, GuestContribution

Updates between 17th of July and 21st of July

Here's an update from Bernard for the past week.

17 July -
I'm not sure there's been any work going on today. Doesn't look like anyone's there now.

IMG_20170717_154716.jpg


18 July -
- formwork build on hotel tower
- pouring blade walls on the N side using a crane bucket
- continuing to dismantle climbing formwork on office core
- formwork supports starting to go up for the first slab of the res tower

IMG_20170718_150343.jpg


19 July -
- SW slab poured on hotel, reinforcing starting to be laid on N side
- the jacking formwork on the office core is still being dismantled. The parts seem to be stacked around the place, so I have no idea why this is happening. I guess we'll find out!
- formwork starting to cover area SE of res core

IMG_20170719_133836.jpg


Continue reading…  

Wed Jul 26 12:36:39 2017
Photos, Construction, Day, GuestContribution

North Quay crane extended, new number 25 painted on the elevator shaft

The elevator on the North Quay side of the construction site has been extended up higher and a the elevator shaft numbering has been increased to 25.
DSC02347_Fotor.jpg


Continue reading…  

Mon Jul 24 23:44:52 2017
Photos, Construction, Day

Updates between 10th of July and 14th of July

Another update from Bernard for the past week, including some ground level photos this time too.

10 July -
- reinforcing being laid SW side of hotel, formwork being completed on N
- '23′ painted on hotel core just below the climbing formwork. I presume this is the floor number, but haven't checked the dwgs
- formwork going up for slab to S of commercial core
- forms being placed for more columns SW of res core

IMG_20170710_120457.jpg


12 July -
- SW slab poured on hotel, reinforcing looks ready for N slab
- formwork has almost completely filled in commercial tower S of core
- scaffolding around res tower nearly complete, looks like all the columns have been poured
- scaffolding being removed from the S side of the podium area. This is very visible from street level (didn't get a pic though)

IMG_20170712_124842.jpg


13 July -
From the intersections of George Street with Ann & Adelaide Streets


IMG_20170713_090303.jpg IMG_20170713_124739.jpg


Continue reading…  

Thu Jul 20 15:05:34 2017
Photos, Construction, Day, GuestContribution